RE wall panel construction procedure & guidelines

Constructing an RE (Reinforced Earth) wall panel is quite straightforward. RE walls are used to retain soil on either side of a structure or road. The construction process of an RE wall panel is remarkably simple, and we will explore it through this article. Let’s get started.

Reinforcement earth wall precast panel construction

what is RE wall ?

The RE wall, also known as the Reinforced Earth wall, gets its name from the use of reinforcement in its construction. This reinforcement is crucial, as it integrates with the concrete, creating a Reinforced Cement Concrete (RCC) structure. The use of reinforcement enhances the wall’s strength and stability, making it highly effective for retaining soil on either side of structures or roads. In this article, we will explore the construction process of an RE wall, highlighting the importance of reinforcement and the steps involved in creating a robust and reliable structure. Let’s dive in.

how to construct RE wall panel?

To construct an RE wall panel, the first step is to prepare the steel reinforcement according to the Bar Bending Schedule (BBS). Begin by preparing the top and bottom steel reinforcements. Place the bottom steel reinforcement on 40mm cover blocks and secure it with binders. Next, place steel chairs on the bottom reinforcement and lay the top steel reinforcement over them, ensuring every joint is tightly secured with binding wire.

In the next step, seal all sides of the steel reinforcement with wooden planks or shuttering plates to create a mold for the concrete. Once the mold is in place, pour the Reinforced Cement Concrete (RCC) into the mold, ensuring it fills all gaps and covers the reinforcement completely. After the concrete has been poured and properly set, the RE wall panel is ready.

The process of constructing an RE wall panel involves meticulous preparation and careful execution. The use of cover blocks, binding wires, and shuttering plates ensures that the reinforcement is correctly positioned and securely held in place. The final concrete pour transforms the carefully arranged steel into a solid, durable RE wall panel, capable of retaining soil effectively on both sides of a structure or road. This detailed procedure highlights the simplicity and efficiency of RE wall panel construction.

conclusion

Four to five days after constructing the RE wall panel, we proceed with the deshuttering process. Using a hydra machine, we carefully lift the panels and position them one by one for soil retention. This method ensures the panels are securely placed and effectively retain soil on both sides of the structure or road. The combination of careful deshuttering and precise placement using hydraulic machinery highlights the efficiency and reliability of RE wall panel construction.